Capital Projects Completed on Time Annually

2015
Derived from the total number of currently active City capital projects and the number completed at or below their scheduled completion time.

As a percentage 68 percent of projects underway in 2015 were completed on time, while in 2016 that number fell slightly to 66 percent, however so too did the total number of projects underway. Overall the on time completion rate remains relatively constant.

To understand how many of the City’s projects are completed on schedule so that we may identify common contributors to project time extensions and mitigate them.